Friday, July 18, 2014

Drainage and Sidewalk Installation along Northwest 19 Street in Lauderhill

Construction period is July 21 to August 7 -

A new drainage system and sidewalk along the south side of NW 19th Street in front of the Continental Apartments in Lauderhill, from July 21 through August 7, barring unforeseen conditions or weather delays.  The project involves the installation of new catch basins, drainage pipe and sidewalk.

The public should be aware of the following:

  • Flaggers will be stationed on each side of the project boundaries to direct east and westbound traffic on NW 19th Street when necessary.
  • Access to the west side of the apartment complex will be limited for a short time.
  • Pedestrian access will be maintained at all times using the existing sidewalks on the north side of NW 19th Street.