Friday, March 28, 2014

Bike Lane on NW 19th Street From SR 7 to Powerline

1.       The scope of the project will be milling 1” and resurface 1” on the exiting roadway. Restripe the road to 10’ travel lane and 4’ bike lane on both side of the road.

1.       The project is scheduled to be advertised for design in May 2014 and the design contract is scheduled to be executed in November 2014.  Based on the Work Program  the budget for design phase 32 is $850,000.00 and the budget for construction phase 52 is $5,503,916.00.